Shares of G R Infraprojects drew attention after the company announced that it has secured the lowest bidder (L1) position for a significant railway infrastructure contract valued at ₹1,897.51 crore.

The project has been awarded under the Engineering, Procurement and Construction (EPC) model, with the tender floated by West Central Railway, Jabalpur.

Project Overview

As per the company’s regulatory filing, the financial bids were opened on February 11, 2026, where G R Infraprojects emerged as the L1 bidder.

The contract involves the development of a new railway line stretching from Km 124/400 to Km 165/380 between Bahari and Gondawali stations in Madhya Pradesh. The work forms part of the larger Sidhi–Singrauli rail connectivity project, aimed at strengthening regional transportation infrastructure.

Scope of Work

The awarded package encompasses comprehensive railway construction activities, including:

  • Extensive earthwork
  • Construction of minor and major bridges
  • Development of key bridges and viaduct structures
  • RCC box-type Road Over Bridges (ROBs)
  • Road Under Bridges (RUBs) and Limited Height Subway (LHS) works
  • Station building construction
  • Tunnel works
  • Track laying and associated miscellaneous activities

The broad scope indicates that the contract represents a complete railway infrastructure execution package rather than a standalone civil component.

Contract Value and Execution Timeline

The total contract value stands at ₹1,897.51 crore. The company is required to complete the project within 900 days from the appointed date of commencement.

Additional Order from NTPC

In addition to the railway contract, G R Infraprojects recently secured another major EPC project worth ₹487.78 crore. The company emerged as the lowest bidder for a Battery Energy Storage System (BESS) project under NTPC’s programme.

This contract pertains to Lot-1 of the BESS initiative and will be executed at NTPC’s Mouda Super Thermal Power Station in Maharashtra. The financial bid for this project was opened on January 16, 2026.

Summary

G R Infraprojects has strengthened its order book by securing the L1 position for a ₹1,897.51 crore railway EPC project in Madhya Pradesh, with execution scheduled over 900 days. The comprehensive contract includes bridges, tunnels, station buildings, and track work under the Sidhi–Singrauli rail link initiative. The company also recently won a ₹487.78 crore NTPC BESS project, further boosting its infrastructure portfolio.

Disclaimer:

This article is intended solely for educational and informational purposes. The securities or companies mentioned are provided as examples and should not be considered as recommendations. Nothing contained herein constitutes personal financial advice or investment recommendations. Readers are advised to conduct their own research and consult a qualified financial advisor before making any investment decisions.

Investments in securities markets are subject to market risks. Please read all related documents carefully before investing.